This question often arises when developers are required to implement SuDS (Sustainable Drainage Systems) that provide multiple benefits and infiltration is a viable option.
Raingardens are among the simplest SuDS features to implement and maintain. They are typically designed to attenuate surface water at ground level, so it would seem logical to have them located in close proximity to a building to collect roof runoff directly from downpipes.
However, Building Regulations Part H states that any infiltration device, such as a soakaway, should be at least 5 metres from a building. While raingardens are not explicitly mentioned in the regulations, they function in a similar way when they allow infiltration. Therefore, the same 5-metre rule should be applied.
Connecting a significant roof area directly to a raingarden which discharges via infiltration could potentially create a new groundwater pathway next to a building and have a detrimental impact on the structure’s foundations. In the event of surcharge or system failure, locating these features too close to a structure could increase the risk of flooding.
Practical solutions include:
It is a common misconception that if hardstanding area is not increasing, then no extra drainage measures are required. The reality is that today’s standards account for climate change and the need to manage flood risk across the wider catchment, which is an increased expectation from LLFAs.
SuDS and attenuation are still required due to:
In summary, even without more impermeable area, SuDS and attenuation measures ensure developments discharge surface water safely, sustainably, and in line with modern climate-resilient standards.
The Environment Agency would typically make this request when a development is located within a floodplain (an area that floods frequently), and where any water displaced by a new building could increase flood risk elsewhere.
In this instance, the EA requires that the volume displaced by a building be compensated within the development, on a level-by-level basis. This means that the lost flood storage must be replaced at the same ground levels as the original floodplain volume; otherwise, the natural way the floodwater behaves (flows and accumulates), will be altered.
For example, if you provide a below-ground tank for water storage, the lower flood ‘volume’ will fill the tank first, so by the time the flood waters reach the higher levels, the tank is already full. This means that having extra compensation at a lower level will not provide any flood risk benefit at the higher ground level.
To satisfy the EA requirements, a comprehensive redesign of external levels is typically required, along with earthworks modelling. This ensures that the flood volume displaced by the buildings is fully compensated within the external areas and matches the original flood elevations, whilst maintaining compliance with the relevant accessibility and highway standards.
It is not recommended and generally not compliant with Building Regulations and NHBC guidance. Inspection chambers or manholes are required to provide access for maintenance, rodding, and repairs. Without them, even a minor blockage can be costly and disruptive to resolve.
If the internal foul water outlet within the building incorporates rodding access, then it remains a possibility to connect directly to a pipe without a manhole / inspection chamber although due to the reduced access one which should ideally be avoided.
Desktop mapping is useful for an initial indication of soil conditions, but it cannot confirm infiltration potential on its own. Ground conditions vary significantly, even within the same site. For example, we have encountered cases where mapping suggested infiltration was not feasible on a site underlain by clay and surrounded by large surface water sewers, however after BRE365 testing we found infiltration rates to be suitable.
As of best practice, there is a general requirement to provide SuDS / attenuation on all new developments regardless whether they are brownfield or greenfield sites.
Whilst SuDS is typically enforced at the planning stage, it does not mean that if a development gets through planning without explicit SuDS mention, it will not later be enforced either by the planners or others.
Typically, later enforcement comes from Building Control or the sewerage undertaker who will decline connection (either direct or indirect connection) to their sewer unless it can be evidenced the development has followed the surface water discharge hierarchy and that if a connection is warranted, it is as close as reasonably practical to greenfield runoff rates. Provision of SuDS is also linked to numerous warranty / insurance / climate change benchmarking protocols (including BREEAM).
Based on the above, it is our strong recommendation that attenuation / SuDS is utilised on all developments.
A CCTV survey confirms the condition and layout of existing sewers and connections. Without this survey, designs may rely on assumptions, which can lead to unexpected costs during construction. In many cases, it has been discovered that existing pipes serving more than one property (and therefore adopted) run beneath proposed foundations or require diversion. In such situations works must be agreed with the relevant sewerage undertaker and can add significate time and cost to a project if not identified early.
Infiltration is always considered first under the SuDS hierarchy as identified within Part H of the Building Regulations. It is the preferred option, but only if it is proven viable under today’s stricter standards.
However, it may not always be possible based on the below:
It is worth noting that standards have changed over time. A system installed years ago might not meet today’s requirements, especially with climate change allowances for more intense rainfall.
In summary, infiltration is the first option on the list, but it may only be used if BRE 365 testing shows it is feasible. If not, other discharge options must be considered.
To determine how much load a proposed road or hardstanding can accommodate, we first need to understand the expected traffic loading over its design life.
This information is typically obtained from the client typically from Automated Traffic Counters (ATR ) survey or otherwise independent study carried out in accordance with DMRB HD 24/06 – Determining MSA for Pavement Design.
The total expected traffic is expressed in terms of million standard axles (MSA). This figure represents the cumulative number of axle loads that the pavement will experience throughout its lifespan. A standard axle is defined as an axle load of 80 kN (approximately 8 tonnes).
Heavy vehicles such as buses and coaches have a far greater damaging effect on pavement structures than lighter vehicles such as cars, motorcycles, or light goods vehicles, which are generally considered negligible for design purposes.
Once the total MSA is obtained for the proposed hardstanding feature in question, the relevant design standards are applied to determine the appropriate materials, size and thickness of the proposed road or hardstanding area.
We use the following design standards depending on pavement type:
If the existing retained roof’s downpipes discharge to the same location as before, then additional attenuation is not typically required for that roof.
Generally, only new hardstanding extents, such as new roofs or new hardstanding areas, would require attenuation.
Building Control Regulations state the following in regard to existing roofs;
As part of planning however, it is often seen as a general requirement, that the proposed discharge rate within a given redline boundary is lower (normally up to at least 50%) than the existing state or otherwise to greenfield runoff rates. To this end, it may sometimes be necessary to attenuate existing roof and hardstanding areas to achieve this due to limitations on flow controls.
Civilistix, promoting Constructive Conversations in Civil Engineering!
News & Views

November 12, 2026
Topographical surveys help identify overland flow routes and low points where water may collect. Accurate survey information supports informed drainage design, flood risk assessment and site layout decisions from the outset.

November 6, 2026
Manhole backdrops can offer excavation savings and design flexibility, but introduce hydraulic and maintenance challenges. Their use requires careful consideration of site constraints, adoption requirements and long-term drainage system performance.

October 29, 2026
Drainage easements can influence building positions, drainage strategies and development costs. Identifying these constraints early helps project teams coordinate site layouts, maintain sewer access and avoid unnecessary redesign or diversions.