July 16, 2024

Visibility is a cornerstone of highway safety, profoundly impacting driver decisions and response times. Insufficient visibility can precipitate accidents, particularly at junctions, crossings, and bends where clear sightlines are indispensable for anticipating hazards and navigating safely. Optimal visibility not only enhances safety but also enhances the comfort and efficiency of road users, facilitating smoother traffic flow and mitigating congestion. In the United Kingdom (UK), comprehensive guidance documents govern highway design, prominently among them the Design Manual for Roads and Bridges (DMRB) and the Manual for Streets (MfS).
The choice between these guidelines typically hinges on road speed. The DMRB guidelines are apt for high-speed roads with an 85th percentile speed exceeding 60 km/h (37mph), while MfS is better suited for roads with an 85th percentile speed below this threshold.
Whilst speed limits of roads give a good approximation of likely vehicle speeds on a given stretch, actual vehicle speeds can be much faster or slower dependent on the character of the road (windy, open, poor surfaced etc) leading to different driver perceptions and speed responses. To this end, actual vehicle speeds for design purposes should be determined via a vehicle speed survey to ascertain the 85th percentile speed.
The key parameter which secures an adequate visibility is the Stop Sight Distance (SSD). The SSD is the minimum distance required for a driver to perceive an object or hazard on the road, apply the brakes, and come to a complete stop safely. This concept is crucial for ensuring that drivers have adequate visibility to react to potential hazards, such as vehicles ahead, pedestrians crossing the road, or obstructions in the roadway. Below are some extracts from DMRB & MfS which set the required SSD based on the road speed.

Figure 1 – Table 7.1 Derived SSDs for streets from Manual for Streets.

Figure 2 – Table 2 from DMRB Volume 6, Section 1, Part 1 – TD9/93.

Figure 3 – Table 3 from DMRB Volume 6, Section 1, Part 1 – TD9/93.
The Stop Sight distance is used to determine the following key parameters in highway design:

Figure 4 – Figure 7.19 from Manual for Streets.

Figure 5 – Figure 7.18 from Manual for Streets.

We have recently experience more and more Lead Local Flood Authorities (LLFAs) querying rainfall data and parameters used for the hydraulic modelling.
In this article we talk about FSR and FEH rainfall Data, Cv values and more. We find out HOW to set up your hydraulic model to avoid post-planning surprises.
FEH and FSR Data
The first parameter to consider when hydraulically modelling drainage networks is whether to use FEH or FSR rainfall data.
Some LLFA’s will identify whether a specific dataset should be used in their SuDS requirements, whilst others do not mention SuDS requirements at all.
FEH is generally considered to be more accurate, due to the data being based on more recent and more detailed rainfall information, however, this methodology does not include sub-hourly events and although extrapolation is possible, flood estimation guidance from the Environment Agency recommends the use of FSR for events under one hour.
To this end, FEH data is now widely accepted as being the preference when designing attenuation system where critical attenuation times are above 60 minutes in duration.
When designing pipe networks where time of concentration / conveyance is typically below 60 minutes (with the 15-minute duration event often being the critical event for pipe sizing), FSR rainfall data is preferred due to sub-hourly rainfall data more heavily included in its research.
In light of the above, we would suggest modelling hydraulic networks (encompassing pipes and attenuation structures) with both FSR rainfall data (for the sub-hourly events i.e. 15, 30 and 45mins) and FEH rainfall data for all events 60+ mins and provide all results to the LLFA.
Whilst it depends on catchment and location of a given site, from our experience FEH-13 and FEH-22 data can easily provide attenuation volumes of 10-15% higher than with FSR data and hence using this data in the wrong context can be costly.
Cv values
The volumetric runoff coefficient – Cv, is the proportion of the rainfall volume materialising within the positive drainage system.
Cv varies depending on the permeability of the catchment, the soil type and the wetness among other factors.
Historically a value of 0.75 and 0.84 was used for summer and winter events respectively (as adopted from the Wallingford Procedure). We however are seeing the accuracy of this approach now scrutinised by LLFAs who request a Cv closer or equal to 1.
We have noticed some LLFA SuDS guidance documentation explicitly request Cv to be set at 1, or to provide evidence of why it should be set lower.
This clearly results in additional attenuation volume when compared to the default values recommended by the Wallingford Procedure and other hydraulic drainage design guidance.
Indeed, whilst designers will explicitly need to follow the Cv values set by LLFAs to gain their approval, it is our view the use of Cv’s approaching 1.00 should be questioned and evidenced.
What are the consequences of using the wrong data sets and parameters?
The used of FEH or FSR and different Cv values, will have a significant impact on the attenuation volumes to be provided.
A significant risk to any project is when a Drainage strategy is submitted for planning using a given size for an attenuation tank or basin. This informs the size of the landscape and architectural design. Subsequently, if planning feedback states that different parameters should be used increasing tanks or basins by as much as 20%, this can have a serious detrimental effect on the masterplan.
How can we design accurately without oversizing our SuDS features?
In summary make sure you have checked parameters with your local council and LLFA and do not assume that the modelling software is correct. CHECK!

This site was for the creation of a new clubhouse and restaurant, venue building and associated external hardstanding area including ~100 space car parking, associated access road and pedestrian accessways & creation of a new groundkeeper’s compound and associated concrete service yard.
Civilistix Consulting Engineers were appointed to initially provide planning condition discharge for all Highway and Drainage items and subsequently to prepare detailed drainage and external hardstanding design packages for tender and construction.

Drainage:
We carried out a detailed surface water drainage design encompassing numerous SuDS components including permeable paving, geo-cellular storage, an attenuation basin and roadside swales. Our surface water drainage design ensured the 100 year plus climate change allowance was accommodated whilst providing exceedance flow to any storm which exceeded this threshold in accordance with current best practice.
An external service yard area was also proposed. Due to runoff from this area being of greater contamination risk, we proposed flows to pass via a full retention oil separator prior to release into the SuDS network.
To accommodate increased foul water effluent, we designed a new foul water pump station which connected to an existing rising main which discharged flows offsite to the Thames water public sewer. Due to the large increase in flows and to guard against pump failure, our design encompassed an offline foul water emergency storage tank.
Highways:
A new access was required from the proposed green keepers’ compound to Evendons Lane, a public highway. This was prepared by Civilistix under a S278 agreement. The S278 works involved the crossing of an Ordinary watercourse. Further to obtaining S278 technical approval of the works, Civilistix engaged with Wokingham Borough Council to obtain approval for the culverting of the Ordinary watercourse.


Rain gardens, also called bioretention facilities, are one of a variety of practices designed to increase rain runoff reabsorption by the soil. They are designed to mimic the natural water retention of undeveloped land and to reduce the volume of rainwater running off into drains from impervious areas as well as treat low level pollution.
What are the BASIC DESIGNS OF RAINGARDENS and what should you look out for:
When raingardens are proposed, it is important to understand what their role will be in the wider drainage strategy of the site. When designed to collect water from rainwater downpipes from buildings, the catchment will be the area of roof associated with each pipe. Where they collect water from adjacent impermeable areas, the design needs to make sure the gradient of the paving will allow enough water to flow towards the raingarden. This is particularly important when retrofitting raingardens in existing urban environments. Often the opportunities for the location of the raingarden are limited, and it may be a challenge to re-design the levels around it to allow water to flow to the raingardens.
If the raingarden is designed to provide drainage for a significant impermeable area, it will probably require a discharge point. When the infiltration of the ground is good enough, the raingardens can be designed for water to infiltrate. It is important to note that the discharge of large areas into a raingarden that infiltrates to the ground, will concentrate flows in a small area and may affect the impact bearing capacity of the ground and nearby structures. In these cases, the raingardens will need to be placed at a safe distance from buildings. A 5-metre distance is typically used for sands and gravels, but this may increase significantly for chalk. If infiltration is not feasible, a piped connection to a surface water sewer or a watercourse is required.
CIRIA Guidance C753 states the plan area of raingardens should be a minimum of 4% of the total catchment area it accommodates. This is to provide a minimum level of water treatment, interception losses and to avoid clogging.
A key consideration in the design of a raingarden is establishing whether the raingarden will provide rainwater attenuation.
If attenuation storage is required, it will be stored within the drainage layer at the bottom of the raingarden. This usually consists of a stone layer with a minimum porosity of 30%, which is generally fully dedicated to water attenuation. To ensure storage is optimised, the use of flow controls may be required to ensure water does not flow out too quickly.
The upper layer, called growing medium, is the material that supports plant growth, and its depth and porosity will vary depending on the plant species, but is typically a minimum of 400mm with 20% void ratio.
Raingardens are eco-friendly and an attractive solution to reducing the negative impact of surface water runoff. They are a small feature that can easily be included in any SuDS design, from a single residential dwelling to a large development.

There is currently a national drive to implement SuDS (Sustainable Drainage solutions) with many sewage undertakers requesting the use of SuDS and evidence the surface water discharge hierarchy has been followed prior to accepting connections to their sewer assets even if not explicitly requested at the planning stage.

So, the question is: What techniques can we use to ensure we comply with SuDS?
SuDS techniques are generally based on natural drainage features to collect, treat, store and then release storm water slowly into the environment.
The following are some techniques used:
Our team of knowledgeable Engineers can help with your sustainable drainage solutions and are up to date on current legislation.

“The engineer has been, and is, a maker of history”
James Kip Finch (American Civil Engineer)
Civilistix Services Offered
Planning services: Planning Services Cambridge | Civilistix
Highway services: Highway Engineering Cambridge | Civilistix
Drainage engineering: Drainage Engineering Cambridge | Civilistix
Surveying services: Surveying Services | Civilistix
News & Views

November 6, 2026
Manhole backdrops can offer excavation savings and design flexibility, but introduce hydraulic and maintenance challenges. Their use requires careful consideration of site constraints, adoption requirements and long-term drainage system performance.

October 29, 2026
Drainage easements can influence building positions, drainage strategies and development costs. Identifying these constraints early helps project teams coordinate site layouts, maintain sewer access and avoid unnecessary redesign or diversions.

October 23, 2026
Safe pedestrian routes require careful coordination where they cross vehicle accesses. We explore how layout, visibility, vehicle speeds, accessibility and drainage help create safe pedestrian crossings.