As we move from sun-filled summer days to cooler fireside evenings (and sometimes back again, just to keep us guessing), we have been reflecting on change here at Civilistix. Stronger partnerships have resulted in more exciting projects, which in turn has meant that our team is growing.  We are proud of our business growth and a bigger team means we can continue to support our clients with the same great quality of work they have come to rely on from us.

In other news of change – our senior civil engineer, Yaré, recently tied the knot! It was a fairytale day and the happy couple looked gorgeous. Congratulations, Yaré!

The discharge hierarchy for surface and foul water is a structured approach that aligns with Building Regulations Part H to promote effective, sustainable water management. The goal of this hierarchy is to minimize flood risks, reduce water pollution, and manage stormwater runoff efficiently. This article provides an overview of the discharge hierarchy as outlined in Building Regulations Part H and explains its importance from a drainage design perspective.

Discharge Hierarchy for Surface Water

Surface water management aims to minimize runoff and prevent pollutants from entering watercourses. The hierarchy for surface water, according to Building Regulations and drainage best practices, is as follows:

  1. Infiltration: The preferred method is to discharge surface water into the ground through infiltration methods, such as soakaways, ponds, or permeable paving. The primary benefit of infiltration is the natural filtration and attenuation of water which reduces strain on public sewer systems. However, infiltration feasibility depends on soil permeability and groundwater levels. Infiltration testing to BRE365 is typically required to demonstrate the feasibility of infiltration discharge.
  2. Discharge to a Watercourse: When infiltration is not viable due to low permeability or high groundwater, the next option is to discharge into a nearby watercourse, such as a river or stream. To prevent erosion or flooding, the discharge rate should be controlled typically to greenfield runoff rates, often through attenuation storage solutions such as detention basins or tanks. Discharge to a watercourse may require local authority or environmental agency approval.
  3. Discharge to a Surface Water Sewer: If neither infiltration nor discharge to a watercourse is feasible, discharging to a public surface water sewer is acceptable. This method should be accompanied by flow restrictions and storage measures to avoid overloading the sewer network, especially during peak rainfall events. Building Regulations advise that this option should be a last resort for surface water disposal.

Discharge Hierarchy for Foul Water

Foul water, unlike surface water, contains contaminants and must be directed to treatment facilities to prevent pollution. Part H1 sets out the hierarchy for foul water disposal as follows:

  1. Connection to a Public Foul Sewer: The first choice for foul water discharge is a direct connection to a public foul sewer. This ensures that wastewater is conveyed to a treatment facility, where it is processed before release. This option is required for new developments within close proximity to a foul sewer. Permission must be obtained from the sewerage undertaker (e.g. Thames Water) via a Section 106 agreement.
  2. Connection to a Combined Sewer: Where a separate foul sewer is unavailable, foul water can be discharged into a combined sewer, which carries both foul and surface water. Combined sewers are common in older urban areas, though they pose a higher risk of overflow during heavy rainfall. In these cases, flow management and careful design are essential to prevent sewer surcharges.
  3. Private Treatment System with Discharge to Ground or Watercourse: In rural areas where connection to a public sewer is not feasible, foul water can be treated on-site using a private sewage treatment system (e.g. septic tank or treatment plant) with discharge to the ground or to a watercourse. This option may require approval from environmental regulators and may be subject to strict discharge quality standards.

From a drainage design perspective, adhering to the discharge hierarchy involves assessing site conditions, soil infiltration capabilities, and proximity to existing sewers or watercourses. The key steps include:

  • Site Investigations and Infiltration Testing: Initial site investigations, including soil permeability testing (e.g. BRE 365, Percolation Tests), help determine the viability of infiltration options.
  • Flow Control and Attenuation Measures: If discharge to a watercourse or sewer is necessary, flow control and attenuation systems like detention basins or modular tanks manage the release rate and prevent downstream flooding.
  • Environmental and Regulatory Compliance: Each discharge method requires compliance with the local regulations and, in some cases, obtaining permits from environmental agencies or local authorities.

Understanding and applying the discharge hierarchy for surface and foul water in alignment with Building Regulations Part H is essential for any development project. This hierarchy not only helps in achieving compliance but also supports sustainable water management practices by prioritizing natural infiltration and sustainable drainage systems (SuDS) over traditional methods. By focusing on reducing runoff and promoting efficient water treatment and discharge, the hierarchy contributes to environmental conservation and long-term infrastructure resilience.

At Civilistix, we can assist you in designing a sustainable and efficient drainage strategy that adheres to the discharge hierarchy specified in Building Regulations and industry best practices.

Civilistix Consulting Engineers were appointed to prepare Private Drainage & External Hardstanding Detailed Design packages. Development proposals were a mixed-use development consisting of commercial space and the creation of 196 residential units arranged over 3-6 storeys along with courtyard area, public realm and other associated external hardstanding area.

We proposed a large geo-cellular storage tank located underneath the courtyard area, permeable paving and a green roof system to attenuate surface water runoff and restrict flows to 3.2l/s before being disposed fully under gravity, to a Thames Water public surface water sewer located within St James Street.

 

Our scope also included Adoptable Highway Design (S278) for the creation of a vehicular access connecting with Brunner Road and the creation of a layby and footway enhancement / public realm along Brunner Road, St James Path and St James Street.

We worked in close collaboration with other design teams, to deliver a fully coordinated proposed private drainage and external hardstanding solution for the client.

Concrete has several advantages as a pavement material, making it a preferred choice for many applications. Its strength and stiffness provide excellent load-bearing capacity, distributing heavy traffic loads with minimal deformation. Concrete pavements are also highly durable, requiring less maintenance over their lifespan compared to flexible options like asphalt. They resist rutting, fuel and oil spills, and high-temperature damage, making them ideal for industrial yards, access roads, and high-traffic areas. When well designed, concrete offers a cost-effective, long-term solution with reliable performance under demanding conditions.

Designing reinforced concrete pavements requires careful consideration of various factors, one of the most critical being the slab thickness. Determining the correct thickness is essential to ensure the pavement’s durability, load-bearing capacity, and long-term performance. The Concrete Society’s Technical Report 66 (TR66) references the Transport Research Laboratory’s Report RR87 (TRL RR87) for calculations related to conventional reinforced concrete slabs.

TRL RR87 is a technical report that presents empirical methods for designing concrete slabs under industrial and commercial traffic loading. The guidance is based on full-scale testing and performance monitoring of pavement trials, combined with back-analysis of field data. The resulting formula was derived by correlating real-world slab behaviour with variables such as load frequency, concrete strength, reinforcement, and foundation support. This data-driven approach underpins the slab thickness formula adopted by TR66 for reinforced concrete pavements.

The slab thickness (h) is calculated using the following empirical formula from TRL RR87:


Each of these parameters plays a significant role in defining the slab’s ability to withstand traffic loads and environmental stresses:

  • Traffic loading (L):Traffic loading refers to the cumulative impact of vehicle axle loads over the design life of the pavement, expressed in millions of standard axles (MSA). To calculate this, refer to the Design Manual for Roads and Bridges (DMRB) document CD 224 – Traffic Assessment, which provides detailed guidance on assessing commercial vehicle loading.
  • Concrete Compressive Strength (ffcm,cube): which correspond to the 28-day compressive strength of the concrete mix. This value is likely to be at least 5 MPA greater than the characteristic compressive cube strength and is usually taken as [characteristic strength + 7MPa] in the calculations of the tabulated values and the factors in the factorial approach.
  • Loaded Area (A): a typical value of 393mm2is typically used, corresponding to a fabric designation A393.
  • Subgrade Reaction Modulus (M): this depend on the type of sub-base used and can be derived from the method described in TR66 Appendix D:
    • 150mm Type 1 sub-base; 33.902 x CBR4547
    • 150mm HBM sub-base; 33.902 x CBR471

Figure D.1 from TR 66: relationship between CBR and Equivalent Foundation Modulus for sub-bases of 150mm HA Type 1 and 150mm HBM

For practical purposes, TR66 recommends rounding up and ensuring a minimum thickness, typically around 150mm for reinforced concrete pavements to account for durability and reinforcement cover.

The graph below illustrates the required slab thickness for different traffic loads, based on a PAV2 concrete (ffcm,cube = 40N/mm2) with A393 mesh and a CBR value of 5%:

Concrete Slab Thickness vs Traffic Loading (MSA)

Conclusion

TR66 provides a practical approach to designing reinforced concrete pavements using empirical data from TRL RR87. By understanding the variables involved and using reliable design tools, engineers can deliver robust, cost-effective pavement solutions that perform well under demanding conditions.

Inspection chambers (or manholes) are essential components of drainage and sewer systems.

These underground structures provide access to pipelines for maintenance, inspection, and cleaning and are a key part of drainage design.

Chamber sizes vary based on several factors including pipe cover depth, pipe size, the number of connections and network simulation requirements. Understanding these factors ensures compliance with regulations and the effective performance of the drainage system.

  1. Pipe cover depth

Pipe cover depth refers to the vertical distance from finished surface level to pipe crown level at any given point along the pipe alignment.

The required pipe cover depth is determined by several factors, including:

  • The material composition of the pipe (e.g. plastic, concrete).
  • The expected load imposed on the surface above the pipe.
  • Proposed bedding and backfilling options.

The UK government’s The Drainage and Waste Disposal: Approved Document H outlines the limits for pipe cover and, bedding and backfill options and specifically refer to:

  • Tables 8 – 11: Pipe cover depth limits based on material composition and installation conditions.
  • Diagrams 10 & 11: Bedding and backfilling options.
  1. Pipe size

Different types of chambers have maximum incoming / outgoing pipe size allowances.  This is primarily based on pre-formed chamber bases and current maintenance requirements.

When determining chamber size, it is important to assess the largest pipe connection (often the outgoing pipe size) as this determines the overall chambers dimensions.

Table 12 of The Drainage and Waste Disposal: Approved Document H  provides guidance on the minimum chamber size relative to the largest pipe it serves.

  1. Number of Connections (incoming pipes)

The number of incoming pipes a chamber can accommodate depends on the chamber’s design and is based on pre-formed chamber bases and current regulatory standards.

It is important to note that the number of pipe inlets for plastic chambers may vary by manufacturer.

  1. Network simulation requirements

While the previous factors determine the minimum required chamber size, in some cases, chambers may need to be oversized. This can be necessary to create additional network storage volume, to help mitigate the risk of flooding within the system.

Conclusion

Selecting the correct private chamber size is essential to ensure an efficient and compliant drainage system. By taking into account the above factors, our civil engineers can design chambers that meet regulatory standards while optimising system performance. A well-designed system not only enhances accessibility for maintenance but also contributes to the long-term reliability of the drainage network.

drainage_in_enhancing_road_safety_header

In the decade leading up to 2021, there were a total of 7847 reported casualties in accidents where the primary cause was ‘poor or defective road surfaces. (tensar.co.uk). Poor drainage of roads is a direct contributor to this statistic.

While the term ‘road safety’ primarily conjures up images of speed limits, traffic signs and drivers’ behaviour, the importance of the correct design of drainage systems is often overlooked. Effective drainage is not just about puddle prevention; it serves as a safeguard for both drivers and the structural integrity of our roads.

Here we explore the key role that drainage design plays in road safety, focusing on practical and technical solutions.

Why drainage matters:

  1. Preventing hydroplaning and improving safety with technical solutions:

One of the most dangerous situations on the road is hydroplaning, where a vehicle loses grip due to a thin layer of water. Some technical solutions to mitigate this risk include:

  • Permeable pavements: utilising permeable asphalt or paving blocks allows water to infiltrate through the surface into a specially designed base layer. This prevents surface water accumulation and enhances tire grip by allowing water to drain away from the road.
  • Channel kerbs: channel kerbs are used to efficiently collect and redirect water away from the road surface, significantly improving drainage efficiency. They incorporate slope and drainage channels that guide water into drainage systems, especially effective in flat or low-lying areas.
  1. Reducing slippery surfaces:

Wet or icy road surfaces can become perilously slippery. Technical solutions to reduce slippery surfaces include:

  • Anti-skid surfaces: these surfaces include specialized aggregates such as high-friction aggregates or porous asphalt. They enhance traction during adverse weather conditions by providing a rougher texture that improves tire grip.
  • Rubberized asphalt: although not commonly used in UK, rubberized asphalt contains recycled tire rubber and provides a more textured and high-friction surface. It not only reduces slipperiness but also contributes to sustainability by reusing old tires, reduces traffic noise levels and has a better durability.
  1. Preventing erosion:

Inadequate drainage can lead to soil erosion around the road’s foundation, which weakens the structure and can result in dangerous sinkholes or structural failures. Technical solutions to prevent erosion include:

  • Gabion baskets: gabion baskets are wire mesh containers filled with stones that are strategically placed on slopes. They provide stabilization, reduce erosion, and promote drainage while allowing vegetation to grow.
  • Geotextiles: geotextiles are engineered materials designed to reinforce soils. They are often applied to slopes and embankments to prevent erosion, ensuring the road’s long-term stability. They provide strength and durability to the soil structure. 
  1. Mitigating flooding:

In regions prone to heavy rainfall, flooding is a significant hazard. Technical solutions to mitigate flooding include:

  • Culverts and ditches: culverts are pipes or conduits that help channel excess water away from the road. Ditches, often equipped with erosion control measures, guide water into culverts. This system prevents flooding by directing water to designated outlets.
  • Detention basins: detention basins are designed to temporarily store excess water during heavy rainfall. They gradually release water, preventing downstream flooding. These basins are engineered with controlled outlet structures, such as hydro-brakes or vortex flow control systems, which regulate the rate of water release, preventing downstream flooding and erosion.

Incorporating these technical solutions requires a deep understanding of local hydrology, soil conditions, and climate. Hydrological studies are essential to design effective drainage systems tailored to specific environmental factors, ensuring road safety by reducing the risk of hydroplaning, improving traction, preventing erosion, and mitigating flooding.

At Civilistix, safety and practicality are important elements in our approach to drainage design. We are committed to implementing innovative solutions that contribute to smoother, safer journeys for all road users.

“The road to success is always under construction.”

Lily Tomlin

 

Civilistix Services Offered

Planning services: Planning Services Cambridge | Civilistix

Highway services: Highway Engineering Cambridge | Civilistix

Drainage engineering: Drainage Engineering Cambridge | Civilistix

Surveying services: Surveying Services | Civilistix

News & Views

Latest Updates

Manhole Backdrops: The Pros and Cons

November 6, 2026

Manhole Backdrops: The Pros and Cons

Manhole backdrops can offer excavation savings and design flexibility, but introduce hydraulic and maintenance challenges. Their use requires careful consideration of site constraints, adoption requirements and long-term drainage system performance.

Why Drainage Easements Matter to Site Layout and Detailed Design

October 29, 2026

Why Drainage Easements Matter to Site Layout and Detailed Design

Drainage easements can influence building positions, drainage strategies and development costs. Identifying these constraints early helps project teams coordinate site layouts, maintain sewer access and avoid unnecessary redesign or diversions.

Designing Safe Pedestrian Routes Across Vehicle Accesses

October 23, 2026

Designing Safe Pedestrian Routes Across Vehicle Accesses

Safe pedestrian routes require careful coordination where they cross vehicle accesses. We explore how layout, visibility, vehicle speeds, accessibility and drainage help create safe pedestrian crossings.