Road Safety Audits in Section 278 Agreements

February 13, 2025

What is a Road Safety Audit?

A Road Safety Audit (RSA) is an independent assessment of the potential road safety issues associated with new or modified highway schemes. It ensures that all designs meet the safety standards outlined in the Design Manual for Roads and Bridges (DMRB) and all other relevant guidances, minimizing risks to road users and ensuring long-term project success.

For projects carried out under S278 Agreements, RSAs are essential in securing approval from the Local Highway Authorities (LHA). These audits are conducted in distinct stages, each aligned with the project lifecycle as defined in the DMRB GG 119:

  • Stage 1: Preliminary Design Audit: This stage occurs after the preliminary design is completed but before detailed design begins. The focus is on identifying high-level safety risks associated with the scheme’s layout. For example, poorly designed junctions may create confusion for drivers, while incorrectly placed pedestrian crossings could increase the risk of accidents. Additionally, lane widths or road alignments that do not consider future traffic volumes or vehicle types can compromise safety.
  • Stage 2: Detailed Design Audit: This stage takes place once the detailed design is complete. At this stage, the audit examines the scheme’s specific features in-depth to identify risks arising from the design details. Examples include inadequate drainage that can lead to hazardous surface water accumulation, gradients that are too steep for safe braking, or insufficient sight distances for drivers. Roadside features, such as poorly placed signs or barriers, can also present hazards if they are not visible or do not meet safety standards.
  • Stage 3: Post-Construction (Pre-Opening) Audit: Conducted after construction but before the scheme opens to road users, this stage assesses how the as-built infrastructure matches the intended design and whether it introduces any unexpected hazards. For instance, improperly installed safety barriers may fail to protect users in an accident, and worn or incorrectly applied road markings can confuse drivers. Lighting conditions can also reveal potential visibility issues, particularly in areas with sharp bends or pedestrian crossings.
  • Stage 4: Monitoring Audit: This stage takes place 12 months after the road or highway scheme opens, evaluating its performance under real-world conditions. Emerging issues might include unforeseen accident hotspots or inappropriate driver behavior, such as speeding in areas where traffic-calming measures were expected to slow vehicles. In some cases, poor landscaping or vegetation growth may obstruct sightlines, while wear and tear on surfaces or markings may compromise safety over time.

It’s important to note that RSAs may be conducted either by private, independent companies or directly by the Local Highway Authority’s in-house team, depending on the LHA’s policies. This highlights the importance of understanding each LHA’s specific policies. Engaging with the LHA early in the project helps clarify their preferred process for RSAs, ensuring compliance and avoiding unnecessary delays.

At Civilistix, we specialize in navigating the complexities of S278 Agreements, including the integration of RSAs at all stages of highway design. If you’re planning a highway scheme or need support with road safety audits, don´t hesitate to get in touch with our team.

 

Civilistix Services:

Adoptable (S278/S38) Highway Design | Civilistix

News & Views

Latest Updates

How Topographical Surveys Inform Drainage Design

November 12, 2026

How Topographical Surveys Inform Drainage Design

Topographical surveys help identify overland flow routes and low points where water may collect. Accurate survey information supports informed drainage design, flood risk assessment and site layout decisions from the outset.

Manhole Backdrops: The Pros and Cons

November 6, 2026

Manhole Backdrops: The Pros and Cons

Manhole backdrops can offer excavation savings and design flexibility, but introduce hydraulic and maintenance challenges. Their use requires careful consideration of site constraints, adoption requirements and long-term drainage system performance.

Why Drainage Easements Matter to Site Layout and Detailed Design

October 29, 2026

Why Drainage Easements Matter to Site Layout and Detailed Design

Drainage easements can influence building positions, drainage strategies and development costs. Identifying these constraints early helps project teams coordinate site layouts, maintain sewer access and avoid unnecessary redesign or diversions.