Sewer Diversion

December 11, 2024

A sewer diversion is required when a proposed development or construction project intersects with, or is in close proximity to, an existing public sewer and it is deemed unsafe to build over it. In such cases, it becomes necessary to alter the sewer’s route to accommodate the development while ensuring the sewer’s functionality is maintained.

The process is governed by Section 185 of the Water Industry Act 1991, which permits developers to request the alteration or removal of public water or wastewater assets.

Most relevant considerations include the following:

  • Size of the sewer:
    For small pipes, typically up to 300mm in diameter, the sewer undertaker may permit the works to be undertaken by the developer, ensuring their easement requirements are met (typically between 3 – 5 m). In contrast, the most challenging scenario arises when the sewer is classified as a ‘strategic sewer.’ In such cases, the sewer undertaker usually assumes responsibility for the diversion works to ensure compliance with technical and safety standards. This will have a significant impact on project timelines, as undertakers may take up to 18 months to finalise the works.
  • Access manholes:
    If access manholes are located within the proposed development site, they may need to be relocated to ensure the sewer undertaker can maintain access for maintenance purposes. Manholes can typically be repositioned to external areas within the site boundary, that are easily accessible or within the public highway. If it can be demonstrated that the sewer remains accessible upstream and downstream of the site post-development, the installation of new manholes may be omitted.
  • Available land for the diversion:
    As a general rule, the diverted sewer must maintain a minimum distance of 3 meters from any buildings. This requirement may pose challenges on some sites, particularly when space is constrained. In such cases, a Build Over Agreement with the sewer undertaker may be necessary to ensure the proposed development does not compromise the sewer or ongoing maintenance activity of it.

Additionally, the design of external areas must be coordinated with the diversion works, as the sewer undertaker generally prohibits the placement of features such as permeable paving or trees directly over their pipes.

If the diversion includes works on 3rd party land, the sewer undertaker may exercise their powers (under Section 98 of the Water Industry Act 1991), to construct it regardless of third-party consent.  It should be noted however exercising S98 powers will have a significant impact on costs and project timelines due to legal implications.

Hydraulic design

Once the above items have been clarified, a detailed hydraulic design needs to be submitted for the approval of the sewer undertaker. The design package will typically consist of the relevant plan and section drawings as well as the calculation package, to ensure the diversion works will not have a detrimental effect on the capacity of the sewer.  The sewerage undertaker will typically expect the capacity of all proposed diverted sewers to be of the same or greater capacity than the existing sewer portion the diversion replaces. If the proposed diverted sewer portion is of a greater length than the existing sewer portion it replaces, to maintain capacity the proposed diverted sewer portion will need to be increased in diameter accordingly, due to the flatter overall gradient which will materialise. This needs to be carefully considered to protect downstream capacity, ensure accurate forecasting of costs and to ensure resultant technical hurdles (such as larger pipes leading to reduced cover) can be accommodated.

At Civilistix, we have extensive expertise in preparing comprehensive design packages for Section 185 submissions. We specialize in liaising with sewer undertakers to secure approvals for designs that ensure the viability and success of your projects.

 

Civilistix Services:

Sewer Diversion & Build-over Agreements | Civilistix

News & Views

Latest Updates

How Topographical Surveys Inform Drainage Design

November 12, 2026

How Topographical Surveys Inform Drainage Design

Topographical surveys help identify overland flow routes and low points where water may collect. Accurate survey information supports informed drainage design, flood risk assessment and site layout decisions from the outset.

Manhole Backdrops: The Pros and Cons

November 6, 2026

Manhole Backdrops: The Pros and Cons

Manhole backdrops can offer excavation savings and design flexibility, but introduce hydraulic and maintenance challenges. Their use requires careful consideration of site constraints, adoption requirements and long-term drainage system performance.

Why Drainage Easements Matter to Site Layout and Detailed Design

October 29, 2026

Why Drainage Easements Matter to Site Layout and Detailed Design

Drainage easements can influence building positions, drainage strategies and development costs. Identifying these constraints early helps project teams coordinate site layouts, maintain sewer access and avoid unnecessary redesign or diversions.