Combined Flood Risk Assessment & Drainage Strategy; Drainage & External Hardstanding Detailed Design Packages
Civilistix was responsible for preparing a Flood Risk Assessment and Drainage Strategy to support the planning submission, as well as the detailed design packages for Drainage, and External Hardstanding. The development comprised a full internal refurbishment of the existing dwelling, a rear extension at lower ground floor level, the construction of a new basement, and the addition of a garden pavilion with associated external hardstanding.
Due to site level constraints, the surface water drainage strategy incorporated a piped network conveying runoff to a geo-cellular attenuation tank and a pump station located within the rear garden. Flows were then pumped to a demarcation chamber in the front garden prior to discharge to the Thames Water combined sewer via the existing connection. The proposed system provided sufficient attenuation for the 1 in 100-year storm event, including a 40% allowance for climate change.
The foul water strategy included a packaged pump station at basement level, lifting flows from the basement and lower ground floor to mitigate the risk of flooding from potential surcharge within the public sewer network.
The site was located within an area at high risk of surface water flooding, with records indicating recent historic flooding events. In response, the drainage strategy incorporated a range of additional resilience measures, including non-return valves on gravity pipework, penstock valves, reprofiling of the front garden to act as a barrier against overland flow from the adjacent road, raised lightwell parapets, and other flood protection features.
Civilistix worked closely with the wider design team to deliver a fully coordinated external works and drainage solution, ultimately supporting the successful grant of planning permission.