Drainage Planning Services, Drainage Detailed Design Services and Highway Detailed Design Services
Civilistix Consulting Engineers were appointed to initially discharge drainage planning conditions and subsequently to prepare the Detailed Private and Adoptable Civils Design. This included Highway S278/S38 and Drainage S104/S106 technical approval packages for a 22-unit residential scheme and associated infrastructure.
Following an instructive Ground Investigation Report, infiltration systems were feasible. We prepared a surface water drainage design which proposed a significant portion of permeable paving to private external hardstanding areas as well as private geo-cellular tanks for each residential unit. We proposed a geo-cellular storage tank to serve the main estate spine road.
We worked with Anglian Water early on to ensure the geo-cellular storage tanks would be suitable for full adoption under S104 of the Water Industry Act. We took into consideration the recently released Design Construction Guidance (DCG) which provided greater onerous on sewerage undertakers to adopt SuDS structures.
Due to site levels and a shallow Foul Water public sewer, we proposed that foul water from the development would be collected via carrier pipes operating via gravity before discharging to a Type 3 foul water pumping station. From there it connected via rising main to an existing foul water sewer within Royston Road.
Civilistix Services: