Combined Flood Risk Assessment (FRA) and Drainage Strategy Report, and Utilities Statement Report
Civilistix Consulting Engineers were appointed to prepare a Combined Flood Risk Assessment (FRA) and Drainage Strategy Report, as well as a Utilities Statement Report to support a planning application for an Acquired Brain Injury Unit development. This consisted of a ground floor and basement (lower ground floor), external open spaces with associated access, landscaping, parking, and perimeter pedestrian and vehicular access ways.
The total site area was 0.743ha. The existing site contained a former industrial development and was classified as a brownfield site.
Our drainage strategy proposed discharging both foul and surface water drainage from the proposed development to the existing Anglian Water foul and surface water sewers. Infiltration was not possible due to the site and ground conditions, nor was there an existing watercourse in close proximity to the site.
Our surface water drainage strategy required permeable paving for all external hardstanding areas, except for minor domestic pathways. Soft standing areas within the lower ground floor court were proposed as permeable construction. A geo-cellular attenuation tank was designed to fully contain runoff during the 100year + 40% critical storm event, including pump emergency storage.
We effectively addressed all challenges, such as the lower ground FFL being below the level of the receiving sewers and collaborated with the client and the rest of the design team to deliver the co-ordinated planning application for approval.
Civilistix Services: