The brief

Civilistix was responsible for preparing the detailed design for drainage, external hardstanding, and the site highway access (secured under a S278 agreement with the Local Highway Authority), for a proposed development comprising 36 residential units, together with car parking, access roads, and associated external works.

What we did

The surface water drainage strategy incorporated swales along the access road and permeable paving within hardstanding areas to provide attenuation and water quality treatment, prior to infiltration via geo-cellular soakaways. Foul water drainage was designed to discharge to the Anglian Water public sewer network.

We also undertook the detailed level design and cut and fill assessment for the site. The steeply sloping nature of the site presented significant challenges in developing a viable level strategy that satisfied best practice guidance, Building Regulations requirements, and highway design standards, whilst also achieving an efficient earthworks balance.

These challenges were addressed through an iterative and detailed design process, incorporating a combination of carefully designed level platforms, engineered embankments, and retaining structures. Close coordination with the client and wider design team was maintained throughout to ensure the proposals remained practical, deliverable, and aligned with the overall development objectives.

The approved Section 278 works included the formation of a new vehicular access onto the existing highway, together with the provision of a 2.0m footway to connect the site with David Collins Drive. The scheme also incorporated a new pedestrian crossing on The Street, linking the internal footway network to the south. Civilistix led coordination with the Local Highway Authority to secure approval and ensure safe site access and connectivity.

Through this comprehensive and collaborative approach, Civilistix successfully delivered a coordinated design solution that addressed complex topographical and drainage constraints, whilst ensuring full regulatory compliance.

 