Pickerells Farm, Dunmow Rd, Fyfield, Ongar

Private Drainage Detailed Design and External Hardstanding Detailed Design

Services offered

  • Private Drainage Detailed Design (RIBA 4/5)
  • External Hardstanding Detailed Design (RIBA 4/5)

The brief

Civilistix Consulting Engineers were appointed to deliver the above-mentioned services for the creation of 5no. residential units along with access road, car parking and associated external hardstanding areas.

What we did

Our external hardstanding detailed design package included the preparation of a surface and kerbing general arrangement plan and corresponding full depth pavement and kerbing construction details. This included the proposed construction make-up and material thicknesses based on underlying ground conditions and the proposed use and potential surface loading of each hardstanding area. Furthermore, we prepared a finished site level plan showing site levels and gradients within all hard and soft standing areas.

Our foul and surface water drainage detailed design package involved discharging to an existing open watercourse as no other suitable outfall locations were available in the vicinity of the site. Proposed foul drainage required treating to Environment Agency standards via the use of a proposed treatment plant discharging to an existing watercourse. The proposed surface water network was designed to accommodate the critical 100yr + 40% design event, draining all roof and external hardstanding. Geo-cellular storage and permeable paving was utilised to attenuate and treat proposed runoff. Both foul and surface water required pumping due to the shallow nature of the watercourse. The existing watercourse required realignment to facilitate proposed works with consent for the works by the Epping Forest District Council.

 

Civilistix Services: